Low-margin jobs: how to track costs and changes during delivery

An accepted quotation does not guarantee a profitable job. For Italian SMEs working on individual contracts, connecting estimates, purchases, labour hours and scope changes can reveal cost overruns before work is completed.

Published2026-11-17 · 5 min
Italian SMEsJob costingMarginsQuotationsCost controlERP
01 / Italian businesses

Italian small businesses are reporting margin pressure

In January 2026, Confartigianato Lombardia published a survey involving 1,366 associated micro and small businesses and craft enterprises.

Some 63% of respondents identified rising production costs among the difficulties they faced in 2025. Business owners also reported that accepting low-margin or below-cost work, and failing to adjust prices as costs increased, were among their poorest decisions.

ISTAT's September 2026 data provides additional context. Industrial producer prices rose 13.8% year over year, largely driven by energy. Excluding energy, domestic producer prices increased by 3.5%.

These figures do not describe the economics of individual contracts. They illustrate why estimates prepared before a job begins can become less reliable as conditions change.

02 / The margin

The quoted price is not the final margin

Consider a small installation company accepting a contract worth €12,000, excluding VAT.

Its estimate includes €9,000 in direct costs for materials, labour and subcontractors. The expected margin is €3,000, or 25% of revenue.

During delivery, the company incurs an additional €800 in materials, €600 in labour and €200 in subcontracted work.

If the agreed contract price remains unchanged, direct costs rise to €10,600. The remaining margin falls to €1,400, approximately 11.7% of revenue.

This is an illustrative calculation of margin after direct costs. Overheads and other costs must still be considered when assessing the overall financial result.

The difference may arise from customer changes, unexpected work, delays or purchasing prices that differ from the original estimate.

The operational difficulty is keeping those changes connected when the information sits across documents, emails, purchasing records and timesheets.

03 / During delivery

Job costing should not end with the final report

Monitoring a contract requires three different financial views.

The first is the accepted estimate, which establishes the original revenue, scope, expected costs and commercial conditions. The approved baseline should remain available after later revisions.

The second is the actual cost incurred. Materials consumed, labour time, subcontracted services and other directly attributable expenses must be assigned to the correct job.

The third is the estimate at completion, which includes expected remaining expenditure and outstanding commitments without counting the same costs twice.

A job may look profitable when only received supplier invoices are considered. Yet outstanding purchase orders, unfinished work and unrecorded labour time may still change the outcome.

The useful comparison is therefore between the original expected margin, the margin implied by recorded actuals, and the projected margin at completion.

04 / Existing systems

Connecting existing business systems

A digital solution does not necessarily require replacing the company's ERP.

The existing system can continue to manage customers, suppliers, purchasing and accounting. A job-level operational layer can connect these records to labour time, progress updates and approved changes.

When a purchasing cost changes or the project manager revises the expected hours, the projected margin can be recalculated.

If it falls below an agreed threshold, the system can flag the variance and show its cause: higher material costs, additional labour, unpriced work or pending change approvals.

Negotiating additional revenue, changing commercial terms and authorising scope modifications remain human responsibilities.

For simple operations, a maintained spreadsheet may be sufficient. Businesses managing multiple concurrent jobs, teams and data sources may benefit from more structured integration.

This builds on our earlier Research Note about integrating an ERP rather than replacing it.

05 / Testing

What needs to be tested

A margin dashboard is only as reliable as the records behind it.

Labour cost rates must be defined consistently. Expenses must be assigned to the right contracts. Purchased materials should not automatically be treated as consumed materials. Customer-requested changes need clear ownership and approval status.

An initial pilot can compare a small sample of jobs against financial results reconstructed by the company's administrative team.

Useful measures include cost-record completeness, time spent preparing job reports, variances detected before completion and differences between projected and final margins.

Software cannot eliminate price increases or unexpected work. Its value depends on making the financial impact visible early enough for the business to respond.

EMPV / TAKEAWAY

Track a job from the accepted estimate through projected cost at completion. Accurate cost attribution and approved changes make margin erosion visible earlier.